Attaching from a Node Not Running poe
The procedure for attaching TotalView to poe from a node that is not running poe is essentially the same as the procedure for attaching from a node that is running poe. Since you did not run TotalView from the node running poe (the startup node), you won’t be able to see poe on the process list in the Root Window and you won’t be able to start it by diving into it.
To place poe in this list:
1
2
Select the File > New Program dialog box, and select Attach to an existing process.
3
Look for the process named poe and continue as if attaching from a node that is running poe.