Use this dialog box to restore and restart all of the checkpointed processes. TotalView initially attaches to the base process, and if there are parallel processes related to this base process, TotalView then attaches to them.
The CLI drestart command performs the same operations as this command.
The name of the previously saved checkpoint file. The name used for the checkpoint file is set using an environment variable, so no value is needed in the
Name field. See your POE documentation for more information.
Under Options, the following options apply:
This option is automatically selected and cannot be unselected. TotalView attaches to parallel processes as they are being created.
If selected, the restart operation tries to use the same hosts as were used when the checkpoint was created. If TotalView cannot use the same hosts, the checkpoint operation fails.If not selected, TotalView uses any available hosts.
Under After Restart, the following options apply:
Parallel processes are held immediately after the location where the checkpoint occurred. TotalView attaches to these created parallel processes.
If you checkpointed a LoadLeveler POE job, you cannot restart it with this command. You must resubmit the program as a LoadLeveler job to restart the checkpoint. You also need to do the following:
After you restart POE, start TotalView and attach to POE. POE tells TotalView when it is time to attach to the parallel task so that it can complete the restart operation.
When doing this, you cannot use the restart the checkpoint using this command. POE will tell TotalView when it is time to attach to the parallel task so that it can complete the restart.